Bathrooms
Partitions are installed and we are ready for students first day! The inspector walked through last weekend and has approved our progress. The permit will stay open until the summer 2026 when bathrooms are completed. Locker room bathrooms are still under construction. Walls are being installed and sheet rock should start soon, allowing us to move into finishes.
North Corridor
Masonry crews have begun placing block on the north connector, continuing the structural integration between the new and existing buildings. Steel is expected to start late next week or early the following.
Tech Ed Addition
Roofing work has started, a major milestone that will allow interior work to proceed and minimize weather impacts. The orange air vapor barrier has been sprayed on the brick exterior. We will begin to prep underground plumbing in the next couple weeks. Once complete this will allow for a slab pour inside.