Union Grove High School Referendum Update

Referendum 2024 Update - 9/2/2025

Bathrooms

  • Partitions are installed and we are ready for students first day! The inspector walked through last weekend and has approved our progress. The permit will stay open until the summer 2026 when bathrooms are completed. Locker room bathrooms  are still under construction. Walls are being installed and sheet rock should start soon, allowing us to move into finishes. 

North Corridor

  • Masonry crews have begun placing block on the north connector, continuing the structural integration between the new and existing buildings. Steel is expected to start late next week or early the following. 

Tech Ed Addition

  • Roofing work has started, a major milestone that will allow interior work to proceed and minimize weather impacts. The orange air vapor barrier has been sprayed on the brick exterior. We will begin to prep underground plumbing in the next couple weeks. Once complete this will allow for a slab pour inside. 


Bathrooms

Bathrooms
Bathrooms
Bathrooms

North Corridor

Corridor

Tech Ed. Addition

Expansion
Expansion
Expansion

Questions & Feedback

Should you have any questions, please feel free to connect.

Tom Johnson
District Administrator
Union Grove Union High School District
johntom@ug.k12.wi.us
262-878-4427

Did someone forward you this email? You can subscribe to the UGHS Referendum Newsletter at https://ugbroncos.com/subscribe.

 You are receiving this email because you subscribed to receive updates regarding the Union Grove Union High School referendum that passed in fall 2024.

Union Grove Union High School, 3433 S. Colony Ave., Union Grove, WI 53182