Union Grove High School Referendum Update

Referendum 2024 Update - 8/04/2025

At the North Connector we completed the last of the wall pours. Waterproofing is ongoing and we will begin to backfill once complete, and the concrete has hit the specified strength. 

In the bathrooms by the gym tile is proceeding. You can see the first of the red accent walls has been installed in the pictures.  We drywalled and began to mud the remainder of the first-floor bathrooms and a few on the second floor. Painting is following close behind and we should have more tile work starting next week. 

The 2nd floor science infill slab has been poured! This is a significant milestone which allows us to begin temporarily reconnecting the HVAC, patch ceilings, and reinstall lights on the 1st floor to be ready for the start of school. 

The Tech Ed. addition foundation walls were completed this week. Exterior masonry started this week. The hydro scaffolds will support the install until the segment of wall is topped out. The hydros will be moved to the next section and so on until we have completed the box shape.

The concrete crew will be moving out for the most part this week making way for the steel crew to move in with the anticipated arrival of the Tech Ed. steel in the next couple weeks.  

2nd Floor Science Wing/Poured Flooring

Flooring

Bathroom Tiling

Tile
Tiling
Tiling

North Entrance & Corridor Foundations Poured

North Entrance
Corridor

Tech Ed. Foundations Walls

Tech
Tech ed.
Tech Ed.

Questions & Feedback

Should you have any questions, please feel free to connect.

Tom Johnson
District Administrator
Union Grove Union High School District
johntom@ug.k12.wi.us
262-878-4427

Did someone forward you this email? You can subscribe to the UGHS Referendum Newsletter at https://ugbroncos.com/subscribe.

 You are receiving this email because you subscribed to receive updates regarding the Union Grove Union High School referendum that passed in fall 2024.

Union Grove Union High School, 3433 S. Colony Ave., Union Grove, WI 53182