Tech Ed Addition
The Tech Ed area has been professionally cleaned and handed over to UGHS. Vehicle lifts have been relocated with new equipment being installed as it arrives.
Old Autos/New BHM
Vehicle lifts have been relocated or removed as required. Mechanical, electrical, and plumbing demolition is ongoing.
North Connector
The connector has been tied into the existing building on the first floor. Metal panel installation is beginning.
Preforming Arts Bathrooms
Demolition is currently underway providing space for the construction of four changing areas and a bathroom.
Second Floor Science
The DOAS units have been turned on and balanced. This allowed for removal of the existing air handler and associated ductwork, which frees the space for wall construction to progress. Both the first floor and the Library are now being served by the DOAS units.
Student Entrance
Temporary walls have been installed to allow Mechanical, electric, and plumbing demolition to begin. This work must be completed before the area can be torn down and new construction can start on the secured student entrance.