Land Update

Union Grove Union High School can take immediate possession of the 80 acres.  UGHS will pay the Jurisdictional offer of $2.4M as a security.  The landowner, through his attorneys, is requesting to not go to Condemnation Commission, but instead go directly to the circuit court.

Construction Update

    • Tech Ed Addition
    • Mechanical, electrical, and plumbing fixture finishes are nearing completion.
    • Car exhaust systems are being relocated.
    • Owner-furnished items have begun arriving on site.
     
    • Engineering & Robotics Space
    • Electrical rough-ins are being installed above the ceiling.
     
    • Third Floor Bathroom
    • Final inspections have been completed and approved.
    • The restroom will be ready for student use on Monday.
     
    • Second Floor Student Bathrooms (Conversion to Staff Bathrooms)
    • Renovation work to convert the existing student bathrooms into staff bathrooms will begin on Monday.

Tech Ed. Addition

Tech Ed Mezzanine

Third Floor Bathrooms

Engineering & Robotics

Second Floor Science

Questions & Feedback

Should you have any questions, please feel free to connect.

Tom Johnson
District Administrator
Union Grove Union High School District
johntom@ug.k12.wi.us
262-878-4427


Find previous updates here: https://www.ug.k12.wi.us/page/referendum-2024

Did someone forward you this email? You can subscribe to the UGHS Referendum Newsletter at https://ugbroncos.com/subscribe.

 You are receiving this email because you subscribed to receive updates regarding the Union Grove Union High School referendum that passed in fall 2024.

Union Grove Union High School, 3433 S. Colony Ave., Union Grove, WI 53182