Tech Ed Addition
Electrical rough-in work is ongoing. A significant amount of progress is scheduled to occur during Winter Break, when students are not in the building.

Third Floor Restrooms
Framing for restrooms T300A and T300B is complete and prepared for hard lid and drywall installation.

Second Floor Science
Overhead ductwork and piping continue to progress. Portions of the Corridor C280 framing are complete and ready for drywall.

Second Floor Library
Phase 1 of ductwork installation supporting the new science addition is underway. Select sections of existing ductwork in the Library have been removed, and installation of the new ductwork has begun.

Drone Photos
Updated aerial images are included showing the Tech Ed Addition and the North Corridor.

Tech Ed. Addition

Third Floor Restrooms

Second Floor Science Renovation

Second Floor Library Renovation

Drone Photos

Questions & Feedback

Should you have any questions, please feel free to connect.

Tom Johnson
District Administrator
Union Grove Union High School District
johntom@ug.k12.wi.us
262-878-4427


Find previous updates here: https://www.ug.k12.wi.us/page/referendum-2024

Did someone forward you this email? You can subscribe to the UGHS Referendum Newsletter at https://ugbroncos.com/subscribe.

 You are receiving this email because you subscribed to receive updates regarding the Union Grove Union High School referendum that passed in fall 2024.

Union Grove Union High School, 3433 S. Colony Ave., Union Grove, WI 53182