North Corridor
Brick veneer installation is complete. The vestibule roof has been completed. Roofing work has begun, including the tie-in to the existing structure, and is currently awaiting installation of air handler curbs. Preparations are underway for the slab-on-grade pour scheduled for November 3.
Tech Ed Addition
CMU installation is complete. MEP rough-in activities have started.
Locker Rooms
Construction is complete and the area is ready for punch list walkthrough and final cleaning.