NORTH CORRIDOR
Brick veneer installation is nearly complete. Electrical rough-in work is ongoing. The MEP tie-in to the greenhouse has been demolished back, allowing for completion of the new structure. Roofing crews have begun tying into the existing building.
TECH ED ADDITION
The slab has been poured. CMU partition wall construction is scheduled to begin shortly. Plumbing rough-in work is underway.
LOCKER ROOM
Tile installation is complete, allowing finish work to begin. Upcoming activities include installation of trim and completion of the punch list.