Union Grove High School Referendum Update

Referendum 2024 Update - 8/13/2025

At the North Connector, we began backfilling along both walls and to its elevation in the hallway. We will be prepping for the slab next week.

In the bathrooms by the gym, tile is proceeding. You can see the first of the red accent walls has been fully installed. Grouting has started in those bathrooms. In the other bathrooms floor tiles are being installed and drywalling is almost complete.

The 2nd floor Science Wing infill slab has been poured, and shoring has been removed from underneath, we are temporarily reconnecting HVAC and working on reinstalling the lights before school starts for the first floor.  The ceiling grid will be replaced on the first floor starting next week in the areas where it was removed.

The Tech Ed addition masonry walls have started, and completed on both east and west sides. The South wall has begun, and masons are moving very proficiently. Masons will then move to the Northside connector area when completed on the South side.

The Ticket Booth is nearly set for our first football game of the season! The concrete pad was poured on Wednesday.

North Corridor

North Corridor
Corridor

Bathroom Tiling!

Tile
Red Tile
Flooring

2nd Floor Science Wing

Pour
Duct Work
Science

Tech Ed. Expansion

Expansion
Bucking Bronco
West Wall

Questions & Feedback

Should you have any questions, please feel free to connect.

Tom Johnson
District Administrator
Union Grove Union High School District
johntom@ug.k12.wi.us
262-878-4427

Did someone forward you this email? You can subscribe to the UGHS Referendum Newsletter at https://ugbroncos.com/subscribe.

 You are receiving this email because you subscribed to receive updates regarding the Union Grove Union High School referendum that passed in fall 2024.

Union Grove Union High School, 3433 S. Colony Ave., Union Grove, WI 53182